Electrical Permit Inspections
- Slab - prior to convery any conduit or piping
- Rough In - prior to covering any wires.
- Verify Building Permit Issuance if required
Note - New construction will have a "meter set", "power on" inspection
prior to the final inspection.
For more information, please call (757) 728-2444.
Mechanical Permit Inspections
- Rough In - prior to covering any ductwork, piping, gas fireplaces/logs.
- Air Test - if gas line is involved, an air test inspection must be made at rough-in and final.
- Final - when ALL mechanical work is completed.
For more information, please call (757) 728-2444.
Plumbing Permit Inspections
- Slab Rough In - prior to covering any ductwork, pipes with concrete.
- Rough In - inspection of ant piping prior to covering up with walls or flooring.
- Final - when ALL plumbing work is completed.
For more information, please call (757) 728-2444.
Building Permit Inspections
- Footing - prior to pouring any concrete.
- Slab - prior to pouring any concrete, verify that any plumbing piping or electrical conduit has been approved.
- Foundation - prior to installing subflooring.
- Framing - prior to installing insulation or sheetrock. Make sure all rough-in inspections for Electrical, Plumbing or Mechanical work has been approved.
- Insulation - after installing insulation, prior to installing sheetrock.
- Final - after ALL work is completed and after ALL electrical, plumbing, or mechanical work has been approved.
For more information, please call (757) 728-2444.